Past -
Present -
Future
Paving the Trail
How it was done.
Tunnel Connection
Making travel through Brainerd easy.
What's Ahead
Future plans and funding needs.
Trail History
From vision to reality.
Paving the Trail

Paving the Paul Bunyan TrailPaul Bunyan took a giant step during the summer of 1995. The first 48 miles of the 100-mile Paul Bunyan Trail was paved with asphalt and opened to hikers, bikers, inline skaters, and snowmobilers.

The paved section extends from Brainerd/Baxter to Hackensack. The unfinished section reaches north to Lake Bemidji State Park, so that the completed trail will ultimately link 16 communities.

The Paul Bunyan Trail showcases some of the area’s pine forests, popular lakes, wildflowers and wildlife. It passes along the shoreline of 21 lakes, through many scenic wetlands, and over bridges crossing four rivers and many streams.

The trail follows a railroad line built in 1893 and abandoned in 1983. The quest to create this recreational trail began shortly after the line was abandoned. Five years later, enough public support had been gathered to bring about legislative authorization. Six more years of effort as a citizen lobbyist were necessary before all aspects of the project were completed and the trail was ready for construction.

Monies were appropriated in stages for the various steps of construction: land appraisal, preliminary engineering, and initial acquisition. Major land acquisition funds were obtained in 1990 and construction funds for bridges and paving in 1994.

When bids were opened, Anderson Brothers was substantially under competing bidders and awarded the contract. Trail supporters were pleased, since the company is known as a great corporate community citizen. Construction began in June of 1995 and was completed on October 7, 1995, two weeks ahead of schedule.

Paving the trail was a more complicated project than most people realize. DNR research shows that surface preparation is the key to providing maximum trail life, so Anderson Brothers’ crews dug up and scarified the entire 48 mile, 14-foot wide trail, which had been hardened by 100 years of heavy pounding. After it was reshaped and compacted, ninety-six thousand tons of Class 5 was added and compacted. The trail was then paved with a 10-foot wide blacktop surface (12 miles of the trail are 8 feet wide due to landscape constraints). The finished thickness is two and a half inches. To complete the job, two feet of class 5 were added to the shoulders.

The Paul Bunyan Trail, at the current length of 80 paved miles, represents the longest paved trail project in one contract not only in the state, but also in the nation.

The trail intersects at Walker with the 47-mile Heartland State Trail. With this connection and other planned extensions, the Paul Bunyan Trail will be part of the largest trail system in the nation. Trail users have already proclaimed that the quality construction of the Paul Bunyan Trail has set a new benchmark for future trails.

 Additional projects include the proposed paving of approximately 12 miles, from Bemidji south to Guthrie, in 2008.

 

 
 


| Main | Trail Maps | Trail Talk | Trail Lodging   | History | Trail Towns |

© 2005 Midwest Captions

Contact Paul

Visit Brainerd Lakes Vacation land

midc_smanim.gif (1885 bytes)Designed By Midwest Captions